Construction Project Management Services and Construction Books
  • Construction Home
  • About Paul Netscher
  • +Construction Books
    • Successful Construction Project Management
    • Building a Successful Construction Company
    • Construction Claims
    • Construction Project Management: Tips and Insights
    • Construction Management: From Project Concept to Completion
    • An Introduction to Building and Renovating Houses
    • The Successful Construction Supervisor and Foreman
    • Designing your ideal home
  • Construction Management Services
  • Book Reviews
  • Contact
  • Blog | Construction Management
  • Site Map
  • Blog | Home Improvement
  • Index of construction articles
  • Useful Links
  • Index Home Improvement

How useful is your construction schedule/program on your project?

22/3/2015

2 Comments

 
Is your construction schedule (program/programme) correct? Do those executing the work understand it?

In a recent post ‘Will your construction project be completed on schedule?’ I discussed possible reasons for construction projects being completed late for reasons due to the contractor and briefly touched on the construction schedule.

A properly constructed schedule is a valuable aid to ensuring your project is completed in the shortest possible time, making the best use of your available resources. Yet, many schedules are poorly prepared, don’t show the pertinent information, or aren’t communicated to the relevant parties.

It’s important a construction schedule is prepared which should:

1.            enable the project to be constructed in the shortest possible time, making efficient use of the available resources, without jeopardising the quality, safety or integrity of the project

2.            take into account any client imposed restraints, such as; interfacing with other contractors, access dates to work areas, working in and around existing facilities and the availability of information

3.            allow for adverse weather events, which could normally be experienced, and during which construction work cannot happen or when productivity is reduced

4.            include for interfacing between the different construction work areas

5.            meet the completion dates that were committed to in the contract (unless the project has changed from the one that was in the tender submission)

6.            allow sufficient time for planning the project and for mobilisation (on some projects it can take four weeks or more to get personnel through the mobilisation process and on to site)

7.            include time for design and drawing approvals as required

8.            adequately show the type of resources required and when they’ll be needed

9.            be approved by the client in writing as soon as possible (without an approved schedule it’s difficult for the contractor to claim for variations, late information, late access and extension of time)

10.        clearly show when access is required to the various work areas

11.        indicate when information is required (a separate ‘information required list’ should be prepared which can be updated weekly and discussed with the client at the progress meetings, so the client can be aware of what information is necessary in the next two weeks and notified when information is issued late or when it’s inadequate or incomplete for construction purposes)

12.        be updated regularly (the update must be done correctly, focusing on the critical path activities rather than the overall percentage complete)

13.        be communicated to the relevant staff so they are aware of the key dates and milestones (Supervisors are often only interested in their section of work and what they need to do in the next couple of weeks, so it’s pointless giving them the entire schedule to the end of the project since in many cases it won’t be read and will only confuse them – rather give Supervisors a snapshot of the schedule pertinent to their work, even perhaps giving it to them in a pictorial form which can be easily read and displayed on their office wall)

14.        if needed, be discussed with Supervisors to make sure they understand what needs to be done and why the sequence and resourcing shown is necessary

Unfortunately some construction project managers don’t treat the construction schedule with the importance it deserves. In fact, some construction companies and project managers just view it as another pesky document that the client requires. Yet, it can be a vital part of the success of your project and invaluable when arguing and settling delay claims with your client.

Other similar relevant articles from the same author include:

'The importance of planning your project'

'Understanding the real cost of delays to your project'

'What you need to know to close out your project successfully'

(Paul Netscher is the author of the acclaimed books ‘Successful Construction Project Management: The Practical Guide’ [a required text for Bachelor of Construction Management at some universities] and ‘Building a Successful Construction Company: The Practical Guide’. Both books are available in paperback and e-book from Amazon and other retail outlets. This article is adapted from information included in these books.)

construction management construction project management
2 Comments
Viola Vignali
12/6/2017 10:31:33 pm

Great post!
I agree with you when you say that a construction schedule has to include time for design and drawing approvals. We just posted an article about why you can't live without a construction programme. You should have a look at it, it can offer you a new angle to what you have already written:
https://geniebelt.com/blog/why-you-cant-live-without-a-construction-programme

Reply
Paul
30/6/2017 04:55:02 pm

Hello Viola, thanks for the useful link, regards Paul

Reply



Leave a Reply.

    As an Amazon Associate I earn from qualifying purchases

    Archives

    January 2023
    October 2022
    August 2022
    June 2022
    May 2022
    March 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014
    April 2014

    Categories

    All

    RSS Feed

    Copyright 2016 - The attached articles cannot be reproduced for commercial purposes without the consent of the author.
    The opinions expressed in the attached articles are those of the writer. It should be noted that projects are varied and different laws and restrictions apply which depend on the location of the contractor and the project. It's important that the reader uses the supplied information taking cognisance of their particular circumstances. The writer assumes no responsibility or liability for any loss of any kind arising from the reader using the information or advice contained herein.
    "I have what I consider some of the best books on construction management."


    Books are available from:
    Amazon.com
    Amazon.co.uk
    takealot.com

    kalahari.com
    Amazon.in
    Amazon.de
    Amazon.fr
    Amazon.it
    Amazon.com.au
    Powell's
    Fishpond
    uread
    bokus
    Amazon.ca
    Amazon.es
    Other retail stores


    Available in paperback or on Kindle

    ​"28 YEARS OF CONSTRUCTION PROJECT MANAGEMENT EXPERIENCE, DEVELOPING SUCCESSFUL CONSTRUCTION PROJECT MANAGERS AND BUILDING SUCCESSFUL CONSTRUCTION COMPANIES"

Construction Books

Successful Construction Project management
Building a Successful Construction Company
Construction Claims: A Short Guide for Contractors
Construction Management: From Project Concept to Completion
Construction Project Management: Tips and Insights
​
Build and Renovate Your Home With Your Eyes Wide Open
Book Reviews

Construction services

Construction Management Services
Paul Netscher
Construction Management Blog
​Home Improvement Blog

Contact
Developing Successful Construction Project Managers.

Building Successful Construction Companies.
30 years of construction project management experience
  • Construction Home
  • About Paul Netscher
  • +Construction Books
    • Successful Construction Project Management
    • Building a Successful Construction Company
    • Construction Claims
    • Construction Project Management: Tips and Insights
    • Construction Management: From Project Concept to Completion
    • An Introduction to Building and Renovating Houses
    • The Successful Construction Supervisor and Foreman
    • Designing your ideal home
  • Construction Management Services
  • Book Reviews
  • Contact
  • Blog | Construction Management
  • Site Map
  • Blog | Home Improvement
  • Index of construction articles
  • Useful Links
  • Index Home Improvement