Construction Project Management Services and Construction Books
  • Construction Home
  • About Paul Netscher
  • +Construction Books
    • Successful Construction Project Management
    • Building a Successful Construction Company
    • Construction Claims
    • Construction Project Management: Tips and Insights
    • Construction Management: From Project Concept to Completion
    • An Introduction to Building and Renovating Houses
    • The Successful Construction Supervisor and Foreman
    • Designing your ideal home
  • Construction Management Services
  • Book Reviews
  • Contact
  • Blog | Construction Management
  • Site Map
  • Blog | Home Improvement
  • Index of construction articles
  • Useful Links
  • Index Home Improvement

the construction project schedule or programme (program)

22/10/2014

1 Comment

 
Picture
"The construction schedule must make efficient use of resources, while finishing the project in the shortest time"
It’s important a construction project schedule is prepared which should:
  1. enable the project to be constructed in the shortest possible time, making efficient use of the available resources, without jeopardising the quality, safety or integrity of the project planning your construction project
  2. take into account any client imposed restraints, such as; interfacing with other contractors, access dates, working in and around existing facilities and the availability of information
  3. meet the project completion dates that were committed to in the contract (unless the project has changed from the one that was in the tender submission)
  4. allow sufficient time for planning the construction project and for mobilisation (on some projects it can take four weeks or more to get personnel through the mobilisation process and on to site) Before starting your next construction project ask these questions
  5. adequately show the type of construction resources required and when they’ll be needed
  6. be approved by the client in writing as soon as possible (without an approved construction schedule it’s difficult for the contractor to claim for variations, late information, late access and extension of time)
  7. clearly show when access is required to the various work areas
  8. indicate when construction information is required (a separate ‘information required list’ should be prepared which can be updated weekly and discussed with the client at the progress meetings, so the client can be aware of what information is necessary in the next two weeks and notified when information is issued late or when it’s inadequate or incomplete for construction purposes)
  9. be updated regularly (the update must be done correctly, focusing on the critical path construction activities rather than the overall percentage complete)
  10. be communicated to the relevant staff so they are aware of the key dates and milestones (Supervisors are often only interested in their section of work and what they need to do in the next couple of weeks, so it’s pointless giving them the entire schedule to the end of the project since in many cases it won’t be read and will only confuse them – rather give Supervisors a snapshot of the schedule pertinent to their work, even perhaps giving it to them in a pictorial form which can be easily read and displayed on their office wall)
  11. if needed, be discussed with Supervisors to make sure they understand what needs to be done and why the sequence and resourcing shown is necessary
Do You Have Good Communication On Your Construction Project?

#constructionmanagement #constructionschedule #constructionprojectmanagement
"What I personally liked about this book were the case studies; they were great." Reader review on Amazon
Picture
​Do you want to learn more about pricing construction projects? Information in this article is contained in 'Building a Successful Construction Company: The Practical Guide' by Paul Netscher

Picture
Paul Netscher has written several easy to read books for owners, contractors, construction managers, construction supervisors and foremen. They cover all aspects of construction management and are filled with tips and insights.
Visit to read more.

The books are available in paper and ebook from most online stores including Amazon.
© 2022 This article is not to be reproduced for commercial purposes without written permission from the author.
1 Comment

planning your construction project

11/10/2014

1 Comment

 
Picture
"It’s important to plan the project thoroughly before starting work"
It’s important to plan the construction project thoroughly before starting work, so the more time available to do this the better. The planning includes:

1. thinking through the construction methodology and ensuring the methods selected will be the most efficient and economical (
How To Select The Appropriate Construction Method To Increase Safety And Efficiency)
2. preparing the project construction schedule (the construction project schedule or programme (program))
3. taking out adequate insurance 
4. deciding what construction work will be self-performed and what will be subcontracted (
choosing a subcontractor)
5. ensuring the required construction resources are available and procured (What you should consider when staffing your construction project. )
6. ordering long-lead items required for the construction project
7. ordering construction materials which will be required to start the project (
Ordering the correct quantity of construction materials)
8. sourcing construction equipment (Become Great at Hiring Equipment for Your Construction Project)
9. arranging the necessary permits 
10. preparing and submitting the required paperwork to the client which may include: 
a. quality plans 
b. safety plans 
c. environmental plans 
d. traffic management plans 
e. method statements 
f. job hazard assessments
"Time spent on planning is time well spent."
​Proper and thorough planning will pay dividends and will save costs and make the management of the project easier. Time spent on planning is time well spent.
#constructionmanagement #constructionprojectmanagement #planningprojects
"Out of all the construction books that I have read this is by far the best one."
Picture
​​Information in this article is contained in 'Building a Successful Construction Company: The Practical Guide' by Paul Netscher

​Paul Netscher has written several easy to read books for owners, contractors, construction managers, construction supervisors and foremen. They cover all aspects of construction management and are filled with tips and insights.
Visit to read more.

The books are available in paper and ebook from most online stores including Amazon.
© 2022 This article is not to be reproduced for commercial purposes without written permission from the author.
Picture
1 Comment

Why is there poor productivity on your construction project?

3/10/2014

4 Comments

 
Picture
"Poor productivity on construction projects is a common problem"
Poor productivity on construction projects is a common problem which results in project delays and increased costs. 

Poor productivity could be a result of:
 
  1. having too many people on the project
  2. the area being too congested or cluttered
  3. poor supervision
  4. waiting for access to work areas
  5. waiting for equipment or materials
  6. having the incorrect equipment or materials
  7. equipment breakdowns (The Alarming Truth about Using Old Construction Equipment)
  8. insufficient equipment to move and lift materials
  9. materials difficult to handle and work with
  10. insufficient resources of one trade and too many of another resulting in one trade waiting for the other to complete their work
  11. workers aren’t sufficiently skilled (Training and mentoring in construction)
  12. workers may be unhappy because of poor working conditions or clashes with other team members, their supervisor or management, which often results in them performing tasks slowly (Is There Bullying on Your Construction Projects)
  13. poor discipline
  14. lengthy meetings with workers or with supervisory staff (project staff meetings - are they adding value to your project?)
  15. the construction project isn’t planned and coordinated and the subcontractors’ and client’s activities impact on the work
  16. poor safety and housekeeping resulting in:
    1. lost time due to incidents
    2. the project being shut down due to poor safety
    3. accidents leading to poor morale
    4. key people being injured and unable to work
    5. tasks being done more slowly (How poor safety costs your construction company money)
  17. fatigue (it’s important to ensure workers don’t work excessive and long shifts or work on rest days and project breaks) Is Overtime Killing Your Construction Project?
  18. a high turnover of personnel which is disruptive, leading to poor productivity because new personnel have to learn the project rules, systems, procedures, and tasks, and work with new team members (High Employee turnover? The sooner you know the better.)
  19. workers are frequently moved between the tasks in the course of the day, resulting in:
    1. lost time when they pack up tools and move, as well as going through safety briefings and explanations of the new task
    2. reduced productivity since they’re unable to gain familiarity with the task or other team members (there’s a learning curve to most tasks and as workers become used to performing a task they usually become more proficient and more productive)
  20. management is indecisive and fail to make timely decisions 
  21. access routes and roads are poorly planned, becoming blocked or restricted
  22. storage and stacking areas aren’t planned and become unsafe or inaccessible
  23. long distances between work areas, the toilets, offices and stores
  24. poor performance of subcontractors (What’s expected of your subcontractors? Do they know?)
  25. work areas have inadequate lighting making it:
    1. unsafe
    2. difficult to ensure the correct quality
    3. leaving dark areas where workers cannot be observed
  26. personnel don’t work their full hours, they may take extended lunch and tea breaks and arrive at the work site a few minutes late and leave early (often this can amount to thirty minutes for each person, every day, so it’s important Project Managers set the right example with their own time-keeping, and enforce good time-keeping on the project from the beginning)
  27. adverse weather such as rain, wind, high temperatures and low temperatures  (steps can be taken to limit the disruption such as; moving workers to other areas, providing adequate protective clothing, allowing sufficient rest breaks, reducing work hours, planning projects to ensure much of the work is done before the onset of poor weather, making buildings weather-tight as soon as possible and lifting items at times of the day when it’s less windy)                         
Picture

How clients impact productivity costing contractors money

Sometimes poor productivity on the construction project is a result of the client. The reasons must be ascertained so measures can be implemented to rectify the situation, or so that variations for the additional costs caused by the client can be submitted. (How clients accidentally sabotage construction projects, and how you can stop it) Reasons may be because of: 
  1. late information
  2. drawing changes resulting in rework
  3. lack of access or late access
  4. the client’s or their subcontractors’ activities impacting the work
When can contractors claim extra costs?

Improving construction productivity is a team effort

​It is important that Supervisors and Project Managers are made accountable for their worker’s productivity. Labour productivity should be monitored on each project on all sections. Feedback must be provided to Supervisors and workers, and suggestions made as to how the productivity could be improved.
​#constructionproductivity #constructionmanagement #constructionprojects

Picture
Picture
Picture
Picture
​Paul Netscher has written several easy to read books for owners, contractors, construction managers, construction supervisors and foremen. They cover all aspects of construction management and are filled with tips and insights.
Visit to read more.

The books are available in paper and ebook from most online stores including Amazon.
© 2022 This article is not to be reproduced for commercial purposes without written permission from the author.
4 Comments

The impact of poor equipment productivity on construction projects

3/10/2014

5 Comments

 
Picture
"Improving the productivity of construction equipment will improve profits"
​On some construction projects, such as earthmoving and road projects, the hire costs of plant and equipment can be significant and improving its productivity can improve the project’s profit. Some Reasons why projects lose money
#constructionmanagement #constructionequipment #constructionproductivity

How poor equipment productivity impacts your construction project

Poor construction equipment productivity:

1. can adversely impact the construction schedule 
How useful is your construction schedule/program on your project?

2. could result in additional construction equipment having to be brought onto the project

3. causes the available construction equipment to have to work longer hours

4. impacts on labour productivity by:
  • resulting in operators working longer hours
​
  • requiring additional operators
​
  • holding up and delaying other construction activities and workers
​How poor labour productivity impacts construction projects

We will look at some reasons for poor construction equipment productivity in a later post.
Construction Equipment Productivity
Picture
​Paul Netscher has written several easy to read books for owners, contractors, construction managers, construction supervisors and foremen. They cover all aspects of construction management and are filled with tips and insights.
Visit to read more.

The books are available in paper and ebook from most online stores including Amazon.
© 2022 This article is not to be reproduced for commercial purposes without written permission from the author.
5 Comments
    As an Amazon Associate I earn from qualifying purchases

    Archives

    January 2023
    October 2022
    August 2022
    June 2022
    May 2022
    March 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014
    April 2014

    Categories

    All

    RSS Feed

    Copyright 2016 - The attached articles cannot be reproduced for commercial purposes without the consent of the author.
    The opinions expressed in the attached articles are those of the writer. It should be noted that projects are varied and different laws and restrictions apply which depend on the location of the contractor and the project. It's important that the reader uses the supplied information taking cognisance of their particular circumstances. The writer assumes no responsibility or liability for any loss of any kind arising from the reader using the information or advice contained herein.
    "I have what I consider some of the best books on construction management."


    Books are available from:
    Amazon.com
    Amazon.co.uk
    takealot.com

    kalahari.com
    Amazon.in
    Amazon.de
    Amazon.fr
    Amazon.it
    Amazon.com.au
    Powell's
    Fishpond
    uread
    bokus
    Amazon.ca
    Amazon.es
    Other retail stores


    Available in paperback or on Kindle

    ​"28 YEARS OF CONSTRUCTION PROJECT MANAGEMENT EXPERIENCE, DEVELOPING SUCCESSFUL CONSTRUCTION PROJECT MANAGERS AND BUILDING SUCCESSFUL CONSTRUCTION COMPANIES"

Construction Books

Successful Construction Project management
Building a Successful Construction Company
Construction Claims: A Short Guide for Contractors
Construction Management: From Project Concept to Completion
Construction Project Management: Tips and Insights
​
Build and Renovate Your Home With Your Eyes Wide Open
Book Reviews

Construction services

Construction Management Services
Paul Netscher
Construction Management Blog
​Home Improvement Blog

Contact
Developing Successful Construction Project Managers.

Building Successful Construction Companies.
30 years of construction project management experience
  • Construction Home
  • About Paul Netscher
  • +Construction Books
    • Successful Construction Project Management
    • Building a Successful Construction Company
    • Construction Claims
    • Construction Project Management: Tips and Insights
    • Construction Management: From Project Concept to Completion
    • An Introduction to Building and Renovating Houses
    • The Successful Construction Supervisor and Foreman
    • Designing your ideal home
  • Construction Management Services
  • Book Reviews
  • Contact
  • Blog | Construction Management
  • Site Map
  • Blog | Home Improvement
  • Index of construction articles
  • Useful Links
  • Index Home Improvement