Construction Project Management Services and Construction Books
  • Construction Home
  • About Paul Netscher
  • +Construction Books
    • Successful Construction Project Management
    • Building a Successful Construction Company
    • Construction Claims
    • Construction Project Management: Tips and Insights
    • Construction Management: From Project Concept to Completion
    • An Introduction to Building and Renovating Houses
    • The Successful Construction Supervisor and Foreman
    • Designing your ideal home
  • Construction Management Services
  • Book Reviews
  • Contact
  • Blog | Construction Management
  • Site Map
  • Blog | Home Improvement
  • Index of construction articles
  • Useful Links
  • Index Home Improvement

Mistakes that impact construction schedules/programmes – part 2

3/12/2015

0 Comments

 
PicturePicture courtesy of Joao Neto

​In a previous article I discussed 10 mistakes that occur in construction schedules or programmes. (Read part 1) These mistakes could mean that the contractor is working to a schedule that is incorrect or unworkable and the project is likely to be completed late.
Here are a few more common errors to avoid:
  1. Making the program fit the client’s contractual dates without considering if it’s possible or how you will make it happen. Some contractors are eager to please the client or owner and will agree to contractual completion dates that are impossible. Careful planning needs to be done to see how the schedule can be made to fit the completion dates. If the dates are impossible the client needs to be advised. Sometimes it may be possible to give the client partial completions and access which may be sufficient for the client to continue their work.
  2. Not allowing for statutory holidays. These holidays can impact the project as workers usually have to be paid additional rates, and some services and suppliers may not be available during these times. Sometimes it is also more than the time lost directly because of the holidays – sometimes projects close a half day earlier the day before holidays, or in some areas there could be a tardy return of all workers which impacts production immediately after the holiday.
  3. Not considering the ground conditions. Excavating in rock can be a slow and difficult process and take much longer than excavating in soft material.
  4. Not getting the client to agree and accept the schedule in writing. The accepted contract schedule/programme will form the basis of delay and acceleration claims. Many clients delay accepting the schedule as it gives them time to issue drawings and get their ‘house in order’ before the contractor is able to lodge their claim
  5. The schedule doesn’t take into account the methodology of construction.
  6. No thought is given to the availability of materials or their rate of delivery.
  7. Safety isn’t considered. This is particularly a concern when cranes have to operate in close proximity to each other, or loads are lifted over working areas and where workers are working above work areas below.
  8. The movement of materials and equipment aren’t considered. Large heavy items may need to be installed before buildings can be closed-up and completed. The movement and handling of materials often causes bottlenecks with production – particularly with high-rise projects, congested sites or projects that are in difficult mountainous terrain such as power transmission lines, bridges, railway tracks, etc.
  9. The scheduler or planner accepts the first schedule they produce. It’s sometimes possible by varying sequencing to change the critical path items. By starting the project elsewhere or tackling it simultaneously from different points it may be possible to shorten the overall project duration. Small changes to a schedule can sometimes make significant changes to the project duration.
  10. The schedule allocates too many activities or trades to happen in an area at the same time. For instance it’s difficult and unproductive to have other trades working in a room where floor tiles are being laid.
Conclusion
The scheduler or planner should be experienced in preparing construction schedules. The project manager should ensure that the schedule takes into account the conditions on the project site, the available resources and the chosen methodologies. Where necessary the key subcontractors should be consulted to ensure that time allocated to their tasks is sufficient.
Preparing the best workable schedule is an art, a science and one that needs expertise and experience.
But of course even a good schedule is worthless if it’s not followed or isn’t updated correctly. But this is a discussion on its own which we will discuss in 2016.

What mistakes and pitfalls have you experienced with project schedules?
 
To read more about the author’s books and find out where you can purchase them visit the pages on this website by clicking the links below:
'Successful Construction Project Management: The Practical Guide'
'Building a Successful Construction Company: The Practical Guide'
'Construction Book reviews'
To read more about the author visit the page 'Paul Netscher'
Want to contact Paul Netscher please enter your details on 'Contacts'
Find out how Paul Netscher can help you at construction management services

Order your books from Amazon
Order your books from Amazon UK
​

© 2015 This article is not to be reproduced for commercial purposes without written permission from the author.

construction management construction project management
0 Comments



Leave a Reply.

    As an Amazon Associate I earn from qualifying purchases

    Archives

    June 2022
    May 2022
    March 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014
    April 2014

    Categories

    All

    RSS Feed

    Copyright 2016 - The attached articles cannot be reproduced for commercial purposes without the consent of the author.
    The opinions expressed in the attached articles are those of the writer. It should be noted that projects are varied and different laws and restrictions apply which depend on the location of the contractor and the project. It's important that the reader uses the supplied information taking cognisance of their particular circumstances. The writer assumes no responsibility or liability for any loss of any kind arising from the reader using the information or advice contained herein.
    "I have what I consider some of the best books on construction management."


    Books are available from:
    Amazon.com
    Amazon.co.uk
    takealot.com

    kalahari.com
    Amazon.in
    Amazon.de
    Amazon.fr
    Amazon.it
    Amazon.com.au
    Powell's
    Fishpond
    uread
    bokus
    Amazon.ca
    Amazon.es
    Other retail stores


    Available in paperback or on Kindle

    ​"28 YEARS OF CONSTRUCTION PROJECT MANAGEMENT EXPERIENCE, DEVELOPING SUCCESSFUL CONSTRUCTION PROJECT MANAGERS AND BUILDING SUCCESSFUL CONSTRUCTION COMPANIES"

Construction Books

Successful Construction Project management
Building a Successful Construction Company
Construction Claims: A Short Guide for Contractors
Construction Management: From Project Concept to Completion
Construction Project Management: Tips and Insights
​
Build and Renovate Your Home With Your Eyes Wide Open
Book Reviews

Construction services

Construction Management Services
Paul Netscher
Construction Management Blog
​Home Improvement Blog

Contact
Developing Successful Construction Project Managers.

Building Successful Construction Companies.
30 years of construction project management experience
  • Construction Home
  • About Paul Netscher
  • +Construction Books
    • Successful Construction Project Management
    • Building a Successful Construction Company
    • Construction Claims
    • Construction Project Management: Tips and Insights
    • Construction Management: From Project Concept to Completion
    • An Introduction to Building and Renovating Houses
    • The Successful Construction Supervisor and Foreman
    • Designing your ideal home
  • Construction Management Services
  • Book Reviews
  • Contact
  • Blog | Construction Management
  • Site Map
  • Blog | Home Improvement
  • Index of construction articles
  • Useful Links
  • Index Home Improvement