Construction Project Management Services and Construction Books
  • Construction Home
  • About Paul Netscher
  • +Construction Books
    • Successful Construction Project Management
    • Building a Successful Construction Company
    • Construction Claims
    • Construction Project Management: Tips and Insights
    • Construction Management: From Project Concept to Completion
    • An Introduction to Building and Renovating Houses
    • The Successful Construction Supervisor and Foreman
    • Designing your ideal home
  • Construction Management Services
  • Book Reviews
  • Contact
  • Blog | Construction Management
  • Site Map
  • Blog | Home Improvement
  • Index of construction articles
  • Useful Links
  • Index Home Improvement

Don't make these 10 rookie construction mistakes

28/3/2016

0 Comments

 
Picture
"Basic construction management 101."
Contractors often make mistakes on their construction projects which almost always cost money, sometimes delay the schedule and on occasion impacts their reputation. Most of these errors should have been avoided – in fact many are basic construction management 101.

Unfortunately, because of a shortage of experienced Construction Project Managers we have people managing construction projects who don’t have the knowledge and experience to know better. 

However, even this shouldn’t be an excuse for some errors, because a little thought should have told them what they were doing was wrong. Often though, these basic errors are caused when experienced Project Managers rush into their projects forgetting the basics, or simply because they were over eager or under pressure to get the project underway.
​#constructionmanagement #constructionprojects #constructionplanning

Picture
Image by Tumisu from Pixabay
"Even experienced Project Managers sometimes rush into their projects forgetting the basics,"

Don’t let these rookie mistakes trip your construction project up.

  1. Starting work without an agreed and signed contract in place. A contract is there to protect both the contractor and the customer. It sets out both parties’ obligations and rights. It stipulates what the contractor must deliver and by when. It also stipulates the frequency and timing of the customer’s payments. Yet, some contractors start work on a construction project without a signed contract in place. Sometimes they have a letter from the customer telling them to proceed with the work. But what does this letter actually say? Does it refer to the pricing documentation? Does it say when the contractor will be paid, and more importantly when the contract document will be issued by the customer? In most cases the answer is no, and the contractor is in effect working without any contract or security. Then, when the contract is finally issued the contractor has little scope to negotiate any terms and conditions they deem unfavorable. The contractor has already completed some work so it’s difficult to walk away from the construction project because then they definitely won’t be paid. Invariably they have to accept the terms and conditions in the contract document even though they disagree with some. Don’t start construction projects without a proper contract
  2. Starting the construction project before all the permits, registrations and authorities are in place. These could include: environmental approvals, licenses, building permits, plan approvals and road closures. We’ve all heard of cases of construction starting only for the city authorities to stop work because the building plans haven’t been approved. In many cases it’s the customer’s duty to apply for these permits and approvals. Contractors often assume the customer has received all the regulatory permissions and even if they haven’t that they’ll be paid for their team to stand should the work be stopped. Unfortunately, contractors aren’t always able to recover all of their standing and disruption costs. Furthermore, the construction team becomes frustrated with the lost time and it’s often difficult to get the team fully motivated and at full production immediately the construction project is allowed to restart.
  3. Failing to have insurances in place before starting. It’s wise to check that all insurances are in place and that your insurer is fully aware of any project quirks and risks. If the customer is providing insurances or guarantees check that these are in place and valid for the construction period. Often insurance policies are only valid for a year so you should note when policies need to be renewed so they don‘t lapse part way through the project. Also notify insurers of any major changes that occur during the construction project which may impact the insurance policy or guarantee. Construction project insurances - what project managers need to know.
  4. Not locating the existing services and utility lines before beginning to excavate. DID WE REALLY CUT A FIBER CABLE? THAT’S GOING TO BE EXPENSIVE! Many customers joke that if they want to locate the service lines such as power and water then they only need to let a contractor start excavating and they’ll immediately dig up a power cable or water line. Of course this really isn’t a joke. It can be dangerous, especially if a gas pipe or electrical cable is broken. It disrupts construction work and probably impacts neighbors who could be without power or water while the problem is fixed. It’s usually expensive to repair – particularly if it’s a fiber optic cable. But it’s not just about knowing where the service lines are, it’s about clearly marking their positions and communicating to the team where they are, and what the risks and implications are of breaking them. I can’t tell you how often we’ve cut through known services on a project because people either didn’t know they were there, they forgot they were there, or were just plain careless. Damaging existing services
  5. Not planning the project properly before starting construction. I can relate endless stories of contractors having to relocate their sheds and huts part way through the construction project because they were placed in the wrong position at the start. Many a time we have cranes on the project which can’t lift the weights required or are too short for the task – usually resulting in extra costs and on occasion even causing accidents. Then there are construction projects that are under resourced or even over resourced, or that plainly haven’t selected the best construction methodology. A day or two spent in planning the construction project at the start will save costs and disruptions later. planning your construction project
  6. Not putting in place a project kickoff. All workers (even those working for subcontractors) should attend a project kickoff meeting before starting work. This is to make them familiar with the project rules, ensure they understand the quality requirements and are informed of the project risks and safety requirements. Site rules and safety requirements vary from project to project. Ensure there is no excuse for workers being unaware of what’s expected from them on your construction project. Site or project inductions
  7. Failing to get instructions in writing. Some customers issue verbal instructions to their contractors. This informality leads to problems. Not only can the contractor misinterpret the instruction, but it also leads to disputes when the customer later denies issuing the instruction, maybe even forgets giving the instruction or possibly the person who gave the instruction wasn’t authorized to give it. Always insist on instructions in writing. A written instruction is also a reminder to the construction team to claim the variation. 15 Rules for construction variation claims and change orders
  8. Trying to be the nice guy and not submitting claims. (MISTER NICE GUY DOES FREE WORK. DON’T BE THAT GUY). Often Project Managers are reluctant to submit change order requests because they are frightened of upsetting the customer or they believe things will work out for the good at the end of the project and the customer will look after them. If you have cause to submit a delay claim or an extra cost submit it as soon as possible. I don’t think I have had ever had a construction project where we didn’t submit a claim for extra work. In most cases these claims were accepted and in some cases the project almost doubled in value. Yet, we invariably completed further projects for the same customer and there were never any ill feelings. Beside which, customers hate surprises later in the construction project when the contractor nears the end and finally realizes they are in trouble and then presents dozens of claims to the customer, many of which should have been submitted months earlier. If you have a rightful claim submit it, you can always be mister nice guy later and withdraw it. Are you working for free on your construction project?
  9. Not planning the installation of services to start with the deepest first. I’m sure we have all experienced city roads that are newly resurfaced and then another contractor comes along and digs the new road up to lay a water main. Unfortunately in construction the same thing sometimes happens. One contractor buries an electrical cable and then another has to install a pipe below the cable. Coordinate the installation of all the services so the deepest go in first and where possible even use common excavations so the project site is disrupted once, instead of multiple times.
  10. Selecting subcontractors and suppliers simply because they are the cheapest. I can’t tell you how many ‘cheap’ subcontractors and suppliers have become very expensive over the course of a construction project. They either couldn’t deliver the quality product in the required time (which resulted in delays, disruption and extra costs) or there were additional costs added for items which they had excluded in their price (items that other contractors and suppliers may have included in their price). It pays to perform a proper adjudication of all quotes to ensure you are comparing ‘apples with apples’, ‘like with like’. In addition ensure that the chosen supplier or contractor has the abilities to deliver a quality product, safely and on time. Time spent on adjudicating quotes properly is time well spent. choosing a subcontractor
Picture
"By being a little smarter, remembering to do the basics right, we can save ourselves a whole lot of trouble later."

Do the basics right and you will save time and money

​Now I’m sure many would say these errors are elementary and they wouldn’t make them. Yet, it’s sometimes surprising the stupid mistakes we all make when we are rushed. But, just as important is to make sure that your team don’t make these errors. By being a little smarter, remembering to do the basics right, we can save ourselves a whole lot of trouble later. The 10 P’s of successful construction project management
​This article was first published on the ClockShark website - Get The Industries' #1 Time-Tracking AppRunning a field service or construction business takes coordination and a great team. With ClockShark you get the industries' #1 timesheet app
Picture
Picture
Picture
Picture
Picture
To read more about the author’s books and find out where you can purchase them visit the pages on this website by clicking the links below:
'Successful Construction Project Management: The Practical Guide'
'Building a Successful Construction Company: The Practical Guide'
'Construction Book reviews'
To read more about the author visit the page 'Paul Netscher'
Want to contact Paul Netscher please enter your details on 'Contacts'
Find out how Paul Netscher can help you

Order your books from Amazon
Order your books from Amazon UK

© 2023 This article is not to be reproduced for commercial purposes without written permission from the author.
construction management construction project management
0 Comments



Leave a Reply.

    As an Amazon Associate I earn from qualifying purchases

    Archives

    January 2023
    October 2022
    August 2022
    June 2022
    May 2022
    March 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014
    April 2014

    Categories

    All

    RSS Feed

    Copyright 2016 - The attached articles cannot be reproduced for commercial purposes without the consent of the author.
    The opinions expressed in the attached articles are those of the writer. It should be noted that projects are varied and different laws and restrictions apply which depend on the location of the contractor and the project. It's important that the reader uses the supplied information taking cognisance of their particular circumstances. The writer assumes no responsibility or liability for any loss of any kind arising from the reader using the information or advice contained herein.
    "I have what I consider some of the best books on construction management."


    Books are available from:
    Amazon.com
    Amazon.co.uk
    takealot.com

    kalahari.com
    Amazon.in
    Amazon.de
    Amazon.fr
    Amazon.it
    Amazon.com.au
    Powell's
    Fishpond
    uread
    bokus
    Amazon.ca
    Amazon.es
    Other retail stores


    Available in paperback or on Kindle

    ​"28 YEARS OF CONSTRUCTION PROJECT MANAGEMENT EXPERIENCE, DEVELOPING SUCCESSFUL CONSTRUCTION PROJECT MANAGERS AND BUILDING SUCCESSFUL CONSTRUCTION COMPANIES"

Construction Books

Successful Construction Project management
Building a Successful Construction Company
Construction Claims: A Short Guide for Contractors
Construction Management: From Project Concept to Completion
Construction Project Management: Tips and Insights
​
Build and Renovate Your Home With Your Eyes Wide Open
Book Reviews

Construction services

Construction Management Services
Paul Netscher
Construction Management Blog
​Home Improvement Blog

Contact
Developing Successful Construction Project Managers.

Building Successful Construction Companies.
30 years of construction project management experience
  • Construction Home
  • About Paul Netscher
  • +Construction Books
    • Successful Construction Project Management
    • Building a Successful Construction Company
    • Construction Claims
    • Construction Project Management: Tips and Insights
    • Construction Management: From Project Concept to Completion
    • An Introduction to Building and Renovating Houses
    • The Successful Construction Supervisor and Foreman
    • Designing your ideal home
  • Construction Management Services
  • Book Reviews
  • Contact
  • Blog | Construction Management
  • Site Map
  • Blog | Home Improvement
  • Index of construction articles
  • Useful Links
  • Index Home Improvement