Construction Project Management Services and Construction Books
  • Construction Home
  • About Paul Netscher
  • +Construction Books
    • Successful Construction Project Management
    • Building a Successful Construction Company
    • Construction Claims
    • Construction Project Management: Tips and Insights
    • Construction Management: From Project Concept to Completion
    • An Introduction to Building and Renovating Houses
    • The Successful Construction Supervisor and Foreman
    • Designing your ideal home
  • Construction Management Services
  • Book Reviews
  • Contact
  • Blog | Construction Management
  • Site Map
  • Blog | Home Improvement
  • Index of construction articles
  • Useful Links
  • Index Home Improvement

Don't make these scheduling (programming) mistakes

9/6/2016

0 Comments

 
​I find construction schedules invaluable on all of my projects. For small projects they could be simple hand drawn bar charts and for large projects they could consist of thousands of linked tasks created using specialist software such as Primavera, Microsoft Project, Candy or similar.

Schedules are useful because:
  1. They inform the construction team of what tasks they should be working on and when.
  2. They advise the customer when they should provide construction information and grant access to the contractor.
  3. They are invaluable for calculating extension of time claims.
  4. Progress of the project can be measured.
  5. A resourced schedule enables the contractor to plan when resources are needed and how many of each resource are required.
  6. Material deliveries can be arranged so they’re delivered before they’re needed.
  7. Subcontractor’s work can be planned so they arrive when they’re needed and complete their work on time.
  8. They can be used to plan cash flow.
  9. Knowing the project duration the contractor can calculate their overhead costs for the project.
  10. A properly planned schedule will avoid clashes or hold-ups on the project caused when the preceding necessary tasks haven’t been completed.
However many construction schedules are poorly prepared and have numerous errors which can mislead both the contractor and the customer. In fact a poorly prepared construction schedule, or a schedule with errors, can be more dangerous than having no schedule at all.

Common scheduling errors
Some of the more common errors include:
  1. Making the schedule fit the customer’s dates even if they aren’t achievable. Usually in the request for price the customer provides the start and end dates for the project. Sometimes contractors simply accept these dates assuming they can complete the project in the time provided, when in fact it’s not possible. On other occasions the contractor ‘squeezes’ their schedule to make their construction time fit within the client’s dates, even when they know it’s impossible to meet these dates. This can be dangerous for many reasons:
    1. Inevitably the contractor cannot finish the project in the allotted time and they not only face the prospect of paying liquidated damages but their reputation is damaged.
    2. The contractor remains on the project longer than allowed in their price resulting in them losing money.
    3. The contractor’s team may become demoralized knowing they can never meet the required dates, knowing no matter how hard they work the client won’t be satisfied with their performance, and in fact even their senior management will blame them for delivering the project late.             ( Contractors shouldn’t commit to dates they cannot achieve. They could either submit an alternative achievable schedule that doesn’t satisfy the client’s dates, or not price the project, or discuss with the customer alternate methods or strategies to enable the customer to get access to parts of the project they require on their required dates.)
  2. Formulating the schedule without considering the construction methodology. Frequently I see schedules which were drawn up by a planner with no input from the construction team. In fact some of these schedules don’t even consider the construction methodology the construction team is using. This is obviously pointless because the project progress is often difficult to measure since the tasks are in a different order, or possibly don’t even appear on the schedule.
  3. Failing to allow for the normal expected weather conditions. Contractors frequently complain of weather delays. But often the weather experienced is normal for that region at that time of the year. Yes, on occasion there are abnormal weather events (something that seems to be occurring more often) which cannot be expected. However, contractors should allow for normal weather interruptions which could include rain, winds, snow and extreme temperatures which could disrupt the project or reduce productivity.
  4. Scheduling individual structures without considering the impact of adjacent structures, or the impact they’ll have on adjacent structures. Many structures on a project are connected in some way. Deeper structures may have to be completed (or certainly brought to the underside) before the neighboring structure can begin. Structures can impact access to the neighboring structures. When preparing a schedule it’s essential to consider the impact of adjacent structures and utility lines on other structures.
  5. Forgetting the project constraints. This should be simple, yet sometimes contractors don’t allow for customer imposed restrictions which could include restrictions on working times and accommodating other contractors or the customers own activities. Sometimes even statutory holidays, when work can’t be done, are forgotten.
  6. Allowing inadequate time for material procurement. Some materials require lengthy procurement periods to allow for design, design approval, preparing drawings, drawing approvals, fabrication and shipping.
  7. Ignoring inspections and testing. Waiting for test results can delay follow-on work. Often the client has to witness completed work or test results before the next activity can begin.
  8. Not allowing for commissioning. On some facilities commissioning can take several weeks. This commissioning may include tying in to existing infrastructure and utilities. It could include passing tests witnessed by the customer or the various authorities, closing out major snags, completing documentation and obtaining permits.
  9. Failing to make allowance for local conditions and productivity. Productivity can vary hugely between countries, and although wage rates may be lower in some places you may need four times as many people to complete the same task in the same time. But productivity also depends on the customer and their operations. Working in an oil and gas processing facility may require far more rigorous quality and safety standards than working in the city. Some facilities have stringent security which can make it difficult to get people, equipment and materials onto the project. Projects working in busy traffic can result in slower progress. But even not being able to find people with the required skills can impact productivity and hamper progress.
  10. The schedule allows, or demands, too many trades having to work in a single area at the same time. Only a finite number of workers and different trades can work in an area at the same time. Fitting more people and activities into a small area doesn’t make the work go quicker – in fact it often results in the work going slower as workers work on top of each other or have to stand-down waiting for others to complete their work. Freshly completed work may be damaged by the follow on trades because the materials haven’t dried or cured resulting in the work having to be redone.
  11. Not updating the schedule correctly or failing to take action when slippage occurs on the project. At times the construction schedule isn’t updated correctly and progress isn’t recorded correctly giving the contractor and the customer misleading information. On occasion when slippage is detected the contractor ignores the information and doesn’t take corrective action, or takes the wrong actions which don’t help. It is essential slippage on the schedule is detected early and the correct actions are implemented to catch up the lost time.
  12. Not conveying the schedule to the team in the field, or to subcontractors.  ......Continue Reading.....    This article was first published on the ClockShark website 
construction management construction project management
0 Comments



Leave a Reply.

    As an Amazon Associate I earn from qualifying purchases

    Archives

    January 2023
    October 2022
    August 2022
    June 2022
    May 2022
    March 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014
    April 2014

    Categories

    All

    RSS Feed

    Copyright 2016 - The attached articles cannot be reproduced for commercial purposes without the consent of the author.
    The opinions expressed in the attached articles are those of the writer. It should be noted that projects are varied and different laws and restrictions apply which depend on the location of the contractor and the project. It's important that the reader uses the supplied information taking cognisance of their particular circumstances. The writer assumes no responsibility or liability for any loss of any kind arising from the reader using the information or advice contained herein.
    "I have what I consider some of the best books on construction management."


    Books are available from:
    Amazon.com
    Amazon.co.uk
    takealot.com

    kalahari.com
    Amazon.in
    Amazon.de
    Amazon.fr
    Amazon.it
    Amazon.com.au
    Powell's
    Fishpond
    uread
    bokus
    Amazon.ca
    Amazon.es
    Other retail stores


    Available in paperback or on Kindle

    ​"28 YEARS OF CONSTRUCTION PROJECT MANAGEMENT EXPERIENCE, DEVELOPING SUCCESSFUL CONSTRUCTION PROJECT MANAGERS AND BUILDING SUCCESSFUL CONSTRUCTION COMPANIES"

Construction Books

Successful Construction Project management
Building a Successful Construction Company
Construction Claims: A Short Guide for Contractors
Construction Management: From Project Concept to Completion
Construction Project Management: Tips and Insights
​
Build and Renovate Your Home With Your Eyes Wide Open
Book Reviews

Construction services

Construction Management Services
Paul Netscher
Construction Management Blog
​Home Improvement Blog

Contact
Developing Successful Construction Project Managers.

Building Successful Construction Companies.
30 years of construction project management experience
  • Construction Home
  • About Paul Netscher
  • +Construction Books
    • Successful Construction Project Management
    • Building a Successful Construction Company
    • Construction Claims
    • Construction Project Management: Tips and Insights
    • Construction Management: From Project Concept to Completion
    • An Introduction to Building and Renovating Houses
    • The Successful Construction Supervisor and Foreman
    • Designing your ideal home
  • Construction Management Services
  • Book Reviews
  • Contact
  • Blog | Construction Management
  • Site Map
  • Blog | Home Improvement
  • Index of construction articles
  • Useful Links
  • Index Home Improvement