Construction Project Management Services and Construction Books
  • Construction Home
  • About Paul Netscher
  • +Construction Books
    • Successful Construction Project Management
    • Building a Successful Construction Company
    • Construction Claims
    • Construction Project Management: Tips and Insights
    • Construction Management: From Project Concept to Completion
    • An Introduction to Building and Renovating Houses
    • The Successful Construction Supervisor and Foreman
    • Designing your ideal home
  • Construction Management Services
  • Book Reviews
  • Contact
  • Blog | Construction Management
  • Site Map
  • Blog | Home Improvement
  • Index of construction articles
  • Useful Links
  • Index Home Improvement

The 10 Biggest Risks Clients and Owners Face On Construction Projects

30/9/2018

1 Comment

 
PictureImage courtesy of Stuart Miles at FreeDigitalPhotos.net
Frequently we hear horror stories of projects that have gone wrong, finished late, gone far over budget (sometimes in excess of double the original estimates), poor quality, accidents, lengthy legal battles and projects that don’t do what they were supposed to do. 

​Construction projects face numerous risks. Understanding these risks could help clients avoid, or mitigate the level of risk on their projects. Clients have different risks to the contractor, and each stakeholder in the project faces a different set of risks. Sometimes these risks are the same for a number of stakeholders – so for instance, if the project is slipping against the construction schedule this could negatively impact both the client, subcontractors and the contractor. One would consider that if the contractor loses money on the project this shouldn’t be a risk for the client, yet, if the contractor loses so much money that they become bankrupt before the project is finished then this could have a major impact for the client, who would almost certainly have to engage another contractor, at additional costs, to complete the project, which would also certainly result in a delay to the project. In addition when contractors lose money their subcontractors, employees and suppliers are also at risk.


Unfortunately, many clients fail to recognise, understand, and mitigate construction project risks, which then frequently leads to an unsuccessful project.
​

The 10 risks clients need to be aware of and take action to minimise.
  1. The final project cost exceeding the project budget. Not only could this make the project nonviable in the long term, but it could even lead to the client becoming bankrupt. Reasons for projects exceeding the budget include:
    1. The budget was incorrect.
    2. The project had numerous changes and variations.
    3. The project increased in scope.
    4. The contractor was delayed by the client’s team.
    5. The contract documents didn’t clearly allocate responsibilities, or the scope of works wasn’t adequately defined.
    6. Unexpected site conditions are encountered which adds to costs. Changed founding conditions can add greatly to costs.
  2. The project is completed late. The client not only gets their project late which means that they can’t earn revenue from the project, or they incur additional costs to use other facilities in the interim. Delayed projects also inevitably incur additional supervision and management costs. Late projects could also result in damage to reputation. Reasons for late completion include:
    1. The scope of the project changes during execution, creating delays and variation claims.
    2. The contractor receives access and information late.
    3. The contractor doesn’t perform.
    4. The project schedule was unreasonable and unachievable.
    5. Bad weather causes delays.
    6. Encountering unexpected ground conditions which requires additional work.
  3. Adverse weather which can delay the project and damage existing and completed work.
  4. Shortage of resources. This could include equipment, materials, people and contractors. A shortage of resources can cause:
    1. Prices to increase.
    2. Delays to the project.
    3. Poor quality work.
  5. Contractors that don’t perform. This can result in:
    1. Poor quality work.
    2. Projects that are finished late.
    3. Poor safety on the project.
  6. A project that doesn’t perform as required. This could be because of:
    1. An unclear scope of work.
    2. A poor design team.
    3. Quality problems with construction.
    4. The client having unreasonable expectations.
    5. The client cut costs unreasonably, removing essential items required for the project to operate successfully.
  7. Poor public perception of the project. This can lead to bad publicity and even protests, legal action and boycotts. Governments have even been brought down by poorly conceived and managed projects. Neighbours can feud for years because of one project. Projects can be delayed and even stopped by irate members of the public.
  8. Poor safety which can result in:
    1. The project being stopped.
    2. Damage to existing infrastructure.
    3. Bad publicity.
    4. Delays to the project.
  9. Incurring excessive or unnecessary costs for the project, even theft. Not achieving value for money.
  10. A major contractor or supplier becoming bankrupt on the project. This could lead to project delays and additional costs while another contractor is sourced. In addition warranties for workmanship and equipment could be worthless.

Avoiding and minimising risks
  1. Projects that exceed budget can be minimised by:
    1. Ensuring that the budget is accurate. Budgets should continually be assessed and updated through the life of the project to take account of all the known information and changes. Check that the budget includes all of the costs and that these costs are an accurate assessment. Where necessary include suitable contingencies and allowances for unknown costs.
    2. Having the correct scope of work for contractors to price.
    3. Minimising changes and variations during both the design phase and during construction.
    4. Carrying out proper research of the project site conditions, including doing ground investigations before construction begins.
  2. Projects are often finished late because:
    1. The construction schedule isn’t realistic. Ensure that the schedule is realistic by employing experienced project managers.
    2. The project schedule doesn’t take account of the client’s operations, project restrictions and the normal expected weather events.
    3. There are changes and variations during the project. Reduce and eliminate changes by ensuring that the project scope is properly prepared and complete and that the contractor has all the information when they price the project.
    4. Progress isn’t monitored during the course of the project. Slippage isn’t addressed and rectified.
    5. Contractors are selected on the basis of their price alone and not on their experience and their available resources for the project.
    6. The project is managed poorly resulting in delays with granting access and issuing information to the contractor.
    7. Poor planning.
  3. Adverse weather can’t be avoided, but steps can be put in place to limit or mitigate the impacts. This could include:
    1. Designing the project so that work that could be impacted by poor weather is assembled and built under cover, or off site. Even redesigning the project to eliminate activities which could be impacted by the weather, for example using different foundation methods could eliminate the requirement to excavate in the rainy season.
    2. Planning the start of the project so it doesn’t begin in the worst weather.
    3. Allowing adequate time in the construction schedule for the normal expected weather.
  4. When there is lots of construction happening in the country, state or region, then there can be a shortage of resources.
    1. Projects can be rescheduled to start when the level of construction falls, which could even make the resources, and consequently the project cheaper.
    2. The project could be designed to make use of modules which could even be constructed in areas where resources are more available. Alternative materials could be used which are more readily available, or which aren’t so labour intensive to install.
    3. The duration of the construction work could be extended to account for the shortage of resources.
  5. Clients often focus on choosing a contractor based purely on their price. However, the cheapest contractor might not end up providing the cheapest project. It is important to select a contractor that has the required experience and skills to deliver the project safely, to the required quality and on time. Clients should check the contractor’s previous projects and clients. They need to review the contractor’s planning for the project and check that their project resources will be adequate.
  6. ....Continue Reading.....

​This article was first published on the ClockShark website. To visit this website and continue reading the article click on the link above.
Please share this post
Picture
​To read more about the author’s books and find out where you can purchase them visit the pages on this website by clicking the links below:
  • '​Successful Construction Project Management: The Practical Guide'
  • 'Building a Successful Construction Company: The Practical Guide'
  • 'Construction Claims: A Short Guide for Contractors'
  • 'Construction Project Management: Tips and Insights'
  • ​'Construction Management: From Project Concept to Completion'
  • and 'Build and Renovate Your Home With Your Eyes Wide Open'
'Construction Book reviews'
To read more about the author visit the page 'Paul Netscher'
Want to contact Paul Netscher please enter your details on 'Contacts'

Find out how Paul Netscher can help you
construction management construction project management
1 Comment
FRC link
25/4/2021 06:41:38 am

Awesome article! Thanks for sharing.

Reply



Leave a Reply.

    As an Amazon Associate I earn from qualifying purchases

    Archives

    January 2023
    October 2022
    August 2022
    June 2022
    May 2022
    March 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014
    April 2014

    Categories

    All

    RSS Feed

    Copyright 2016 - The attached articles cannot be reproduced for commercial purposes without the consent of the author.
    The opinions expressed in the attached articles are those of the writer. It should be noted that projects are varied and different laws and restrictions apply which depend on the location of the contractor and the project. It's important that the reader uses the supplied information taking cognisance of their particular circumstances. The writer assumes no responsibility or liability for any loss of any kind arising from the reader using the information or advice contained herein.
    "I have what I consider some of the best books on construction management."


    Books are available from:
    Amazon.com
    Amazon.co.uk
    takealot.com

    kalahari.com
    Amazon.in
    Amazon.de
    Amazon.fr
    Amazon.it
    Amazon.com.au
    Powell's
    Fishpond
    uread
    bokus
    Amazon.ca
    Amazon.es
    Other retail stores


    Available in paperback or on Kindle

    ​"28 YEARS OF CONSTRUCTION PROJECT MANAGEMENT EXPERIENCE, DEVELOPING SUCCESSFUL CONSTRUCTION PROJECT MANAGERS AND BUILDING SUCCESSFUL CONSTRUCTION COMPANIES"

Construction Books

Successful Construction Project management
Building a Successful Construction Company
Construction Claims: A Short Guide for Contractors
Construction Management: From Project Concept to Completion
Construction Project Management: Tips and Insights
​
Build and Renovate Your Home With Your Eyes Wide Open
Book Reviews

Construction services

Construction Management Services
Paul Netscher
Construction Management Blog
​Home Improvement Blog

Contact
Developing Successful Construction Project Managers.

Building Successful Construction Companies.
30 years of construction project management experience
  • Construction Home
  • About Paul Netscher
  • +Construction Books
    • Successful Construction Project Management
    • Building a Successful Construction Company
    • Construction Claims
    • Construction Project Management: Tips and Insights
    • Construction Management: From Project Concept to Completion
    • An Introduction to Building and Renovating Houses
    • The Successful Construction Supervisor and Foreman
    • Designing your ideal home
  • Construction Management Services
  • Book Reviews
  • Contact
  • Blog | Construction Management
  • Site Map
  • Blog | Home Improvement
  • Index of construction articles
  • Useful Links
  • Index Home Improvement